| Klondike III Wind Project |
|
|
 |
|
|
Facility: A wind energy facility with 176 wind turbines and a combined peak generating capacity of approximately 300 megawatts.
Location: Sherman County
Status:
The facility is operating.
Certificate Holder:
Klondike Wind Power III, LLC
Contact:
Kathi Kazala
Klondike Wind Power III, LLC
c/o Iberdrola Renewables, Inc.
1125 NW Couch St., Suite 700
Portland, OR 97209
503-796-6913
Oregon Department of Energy Staff: John White
Original site certificate signed: July 12, 2006
Current site certificate: Fourth Amended Site Certificate (effective March 30, 2011)
History:
- February 17, 2005: Applicant submitted a request for expedited review.
- March 28, 2005: Department of Energy approved expedited review.
- May 13, 2005: Application received.
- February 6, 2006: Application completed (date of filing).
- April 18, 2006: Department of Energy issued a draft proposed order.
- May 31, 2006: Department of Energy issued a proposed order.
- June 13, 2006: Department of Energy issued a supplemental proposed order.
- June 30, 2006: Council approved a site certificate.
- July 31, 2006: Request for Amendment #1 received.
- October 2, 2006: Department of Energy issued a proposed order on Amendment #1.
- October 23, 2006: Start of construction.
- November 3, 2006: Council approved Amendment #1.
- November 8, 2006: Effective date of First Amended Site Certificate.
- April 12, 2007: Request for Amendment #2 received.
- June 19, 2007: Department of Energy issued a proposed order on Amendment #2.
- June 25, 2007: Request for Amendment #3 received.
- July 27, 2007: Council approved Amendment #2.
- August 1, 2007: Effective date of Second Amended Site Certificate.
- October 11, 2007: Department of Energy issued a proposed order on Amendment #3.
- October 16, 2007: Start of commercial operation (123 Phase 1 turbines).
- November 16, 2007: Council approved Amendment #3.
- November 27, 2007: Effective date of Third Amended Site Certificate.
- March 17, 2008: Start of commercial operation of the Mitsubishi 2.4-MW turbine (Phase 1).
- June 21, 2008: Start of commercial operation of Phase 2 (51 turbines).
- December 6, 2010: Request for Amendment #4 received.
- February 15, 2011: Department of Energy issued a proposed order on Amendent #4.
- March 25, 2011: Council approved Amendment #4.
- March 25, 2011: Council approved mitigation plan for raptor fatality rate exceedence.
- March 30, 2011: Effective date of Fourth Amended Site Certificate.
Documents:
- Final Order on the Site Certificate, June 2006 [732 kb pdf]
Attachment A (Wildlife Monitoring and Mitigation Plan) [115 kb pdf] Attachment B (Revegetation Plan) [43 kb pdf] Attachment C (Habitat Mitigation Plan) [49 kb pdf] Attachment D (Draft ODOT Utility Permit) [98 kb pdf]
- Site Certificate, July 2006 [143 kb pdf]
- Final Order on Amendment #1, November 2006 [575 kb pdf]
Attachment A (Wildlife Monitoring and Mitigation Plan) [116 kb pdf] Attachment B (Revegetation Plan) [43 kb pdf] Attachment C (Habitat Mitigation Plan) [48 kb pdf]
- First Amended Site Certificate, November 2006 [150 kb pdf]
-
Attachment B (Revegetation Plan revisions) [43 kb pdf]
Attachment C (Habitat Mitigation Plan revisions) [48 kb pdf]
- Second Amended Site Certificate, August 2007 [150 kb pdf]
- Final Order on Amendment #3, November 2007 [548 kb pdf]
Attachment A (Wildlife Monitoring and Mitigation Plan) [116 kb pdf] Attachment B (Revegetation Plan) [43 kb pdf] Attachment C (Habitat Mitigation Plan) [48 kb pdf]
- Third Amended Site Certificate, November 2007 [165 kb pdf]
-
-
-
-
- Final Order on Amendment #4, March 2011 [483 kb pdf]
- Fourth Amended Site Certificate, March 2011 [168 kb pdf]
- Order Approving Mitigation Plan, April 2011 [13 kb pdf]
- Phase 2 Wildlife Monitoring Study (August 2008–August 2010) [1.6 MB pdf]
|
|
| |
|
|