Klondike III Wind Project
Facility:
A wind energy facility with 176 wind turbines and a combined peak generating capacity of approximately 300 megawatts.
 
Location: Sherman County
 
Status:
The facility is operating.
 
Certificate Holder:
Klondike Wind Power III, LLC
 
Contact:
Kathi Kazala
Klondike Wind Power III, LLC
c/o Iberdrola Renewables, Inc.
1125 NW Couch St., Suite 700
Portland, OR 97209
 
503-796-6913
 
Oregon Department of Energy Staff: John White
 
Original site certificate signed: July 12, 2006
 
Current site certificate:  Fourth Amended Site Certificate (effective March 30, 2011)
 
History:
  • February 17, 2005: Applicant submitted a request for expedited review.
  • March 28, 2005: Department of Energy approved expedited review.
  • May 13, 2005: Application received.
  • February 6, 2006: Application completed (date of filing).
  • April 18, 2006: Department of Energy issued a draft proposed order.
  • May 31, 2006: Department of Energy issued a proposed order.
  • June 13, 2006: Department of Energy issued a supplemental proposed order.
  • June 30, 2006: Council approved a site certificate.
  • July 31, 2006: Request for Amendment #1 received.
  • October 2, 2006: Department of Energy issued a proposed order on Amendment #1.
  • October 23, 2006: Start of construction. 
  • November 3, 2006: Council approved Amendment #1.
  • November 8, 2006: Effective date of First Amended Site Certificate.
  • April 12, 2007: Request for Amendment #2 received.
  • June 19, 2007: Department of Energy issued a proposed order on Amendment #2.
  • June 25, 2007: Request for Amendment #3 received.
  • July 27, 2007: Council approved Amendment #2.
  • August 1, 2007: Effective date of Second Amended Site Certificate.
  • October 11, 2007: Department of Energy issued a proposed order on Amendment #3.
  • October 16, 2007: Start of commercial operation (123 Phase 1 turbines). 
  • November 16, 2007: Council approved Amendment #3.
  • November 27, 2007: Effective date of Third Amended Site Certificate.
  • March 17, 2008: Start of commercial operation of the Mitsubishi 2.4-MW turbine (Phase 1).
  • June 21, 2008: Start of commercial operation of Phase 2 (51 turbines).
  • December 6, 2010: Request for Amendment #4 received.
  • February 15, 2011: Department of Energy issued a proposed order on Amendent #4.
  • March 25, 2011: Council approved Amendment #4.
  • March 25, 2011: Council approved mitigation plan for raptor fatality rate exceedence.
  • March 30, 2011: Effective date of Fourth Amended Site Certificate.   
 
Documents: